HYDE PARK WASTEWATER SYSTEM UPGRADES
06.17.20

Contractor N.A. Manosh installs four fiberglass tanks on June 12, 2020 as part of a new wastewater treatment system. The tanks being installed in this photo range from 4,000 gallons to 20,000 gallon capacity.
The system is replacing a 28 year old onsite wastewater system that serves a portion of the Village of Hyde Park. The new facilities include preliminary treatment followed by a recirculating packed bed filtration in modular AdvanTex units supplied by Orenco. Final disposal is to pressure distribution leachfields with (10) 94 ft long trenches.